Project Completion Determines Mechanics Lien Recording Deadline


The California mechanics lien is one of the most powerful collection remedies available to contractors, subcontractors and suppliers who are unpaid for work performed and materials supplied in relation to a California private works construction project. The mechanics lien allows the claimant to actually sell the property where the work was performed in order to obtain payment. The recording of a mechanics lien is entirely of course, against the wishes of the property owner. There are a number of important steps to follow and timelines to be met in order to pursue this remedy.

First, Understand Your Preliminary Notice Deadline

Working within deadlines is absolutely crucial to preserving mechanics lien rights under California law. The deadlines differ, depending on whether you are a “direct” contractor, also known as “original” or “prime” contractor (one who contracts directly with the property owner) or a subcontractor or material supplier. The process begins with the serving of a “preliminary notice” no later than 20 days after the party serving the preliminary notice begins supplying labor or materials to the project.  Direct contractors are only required to serve the preliminary notice on the construction lender, if any (Civil Code section 8200-8216), whereas subcontractors and material suppliers must serve not only the construction lender, but also the owner and direct contractor (see Civil Code section 8200(e)). 

Note: While Civil Code section 8204 specifies the last possible date on which to properly serve the preliminary notice, it does not specify a date which would be too early to serve the preliminary notice. The subcontractor or material supplier should establish mechanisms so that at some point between execution of a contract and the commencement of work or the supplying of materials the preliminary notice is properly served.

Procedure and Deadline for Service of a Preliminary Notice:
Within 20 days after first furnishing labor, materials or equipment to a jobsite, the subcontractor or material supplier must fill out and send a preliminary notice to the original contractor, owner and the lender, if any. Direct contractors need only serve the construction lender, if any, within the same time period. The notice should be sent by either registered mail, certified mail, return receipt requested, by express mail or overnight delivery by an express service carrier. The notice can also be hand-delivered. However, certified mail, registered mail or overnight delivery are strongly recommended because these methods provide a form of objective documentary proof of delivery. Before sending out the notice, always make a copy of the fully completed notice for your records. Staple your “receipt for certified mail” or other proof of delivery to your copy of the preliminary notice and keep it in a separate folder for the particular job. Later, after the post office or other service returns a return receipt or its equivalent to your office, staple that return receipt to your copy of the preliminary notice and return it to your job file. It is important to safeguard these documents since they may be needed to prove your effort to deliver the preliminary in court at a later time (See Civil Code sections 8200-8216).

Note: In projects where the contract is for over $400, failure of the subcontractor to give the preliminary notice may also subject the subcontractor to disciplinary action with the Contractors’ State License Board. (See Civil Code sections 8216, 8410; see also Civil Code sections 8200-8216.). It is very rare that the CSLB will take such action.

Direct (Prime or Original) Contractor Deadline to Record a Mechanics Lien

If a Valid Notice of Completion or a Notice of Cessation Has Been Recorded:
If a valid “notice of completion” or “notice of cessation” has been recorded with the County Recorder in the County where the work of improvement is physically located, the direct (prime) contractor has 60 days after the date on which such notice was recorded before which the direct (prime) contractor must record a mechanics lien. (See Civil Code sections 8050, 8188, 8182, 8184, 9204, 9208).

Note that a notice of completion is generally valid only if recorded within 15 days after actual completion of the work of improvement. A valid notice of cessation may generally be filed only after work on the work of improvement has stopped for a continuous period of 30 days, even though the project is not completed. (See Civil Code sections 8050, 8188, 9202, 8182, 8184, 9204, 9208)

If No Notice of Completion or Notice of Cessation Has Been Recorded:
If no notice of completion or notice of cessation has been recorded as to the work of improvement, or if the notice of completion or notice of cessation is not valid (usually for violating the recording deadlines noted above), then contractors, subcontractors and suppliers alike all have 90 days after work on the project is completed by all trades before which they must record a mechanics lien. This 90-day period may be extended in cases where, although the project is not fully completed, the work on the project has stopped for a continuous period of 60 days and neither the owner nor the owner’s agent has accepted the project or moved onto the premises. (See Civil Code sections 8180, 9200, 8412, 8414, 8028, 8018 and 8046.)

Deadline for Subcontractor or Material Supplier to Record a Mechanics Lien

If a Valid Notice of Completion or a Valid Notice of Cessation Has Been Recorded:
If a valid notice of completion or notice of cessation has been recorded on the project, subject to the exception noted below in regard to Civil Code 8200 et seq. and 8190, the claimant may have as few as 30 days after the date on which such notice was recorded before which the claimant must record a mechanics lien (See Civil Code sections 8188, 9202, 8182, 8184, 9204, 9208, 8050, 8414, 8186.)

Note again that a notice of completion is generally valid only if filed within 15 days after actual completion. A notice of cessation may generally be filed only after work on the work of improvement has stopped for a continuous period of 30 days (See Civil Code sections 8188, 9202, 8182, 8184, 924, 9208, 8050, 8414, 8186.)

Deadline Extended if Claimants Not Notified of Notice of Completion or Notice of Cessation: An exception to the 30-day rule for recording a mechanics lien by a subcontractor or supplier after a valid notice of completion or notice of cessation can be found in Civil Code sections 8190, 8412-8414. These code sections require private project owners to notify subcontractors and suppliers within 10 days after recording a notice of completion or notice of cessation that the document has been recorded. In order to receive such notice, the subcontractor or supplier must properly use and serve the preliminary notice. If this properly occurs and the private project owner provides the required notice to the subcontractor or supplier, then the subcontractor or supplier will have only 30 days to record a mechanics lien. If an owner, however fails to properly notify a subcontractor or supplier within 10 days after recording a notice of completion or notice of cessation, then the subcontractor or supplier will have 90 days to record a mechanics lien. The details of the law can be found in California Civil Code sections 8190, 8412-8414.

Please note that this law does not apply to public works projects or owner-occupied personal residences of less than 5 units. Moreover, the law does not apply to those subcontractors and suppliers who fail to serve a preliminary notice or, of course, when no notice of completion or notice of cessation has been recorded.

Note: Even though a material supplier may have a contract directly with the owner of the property in question, the material supplier still does not thereby fall into the category of a “direct”, “prime” or “original” contractor within the definition of Civil Code section 8018. Therefore, even a material supplier who has a contract directly with the owner must record its mechanics lien within only 30 days after a valid notice of completion has been recorded as is required by Civil Code section 8414. Such a supplier cannot take advantage of the 60-day deadline available to direct contractors even though the supplier, like the direct contractor, has a contract directly with the owner. A supplier is a supplier and does not become an original contractor simply by having a contract with the owner. See Sparks v. Butte County Gravel Mining Co. (1880) 55 Cal. 389, Vaughn Materials v. Security Pacific National Bank (1985) 170 Cal.App.3d 908, 216 Cal.Rptr. 605.

A free and suitable preliminary notice – private works form can be found at www.porterlaw.com. There are many manufacturers of such forms. Not all such forms have the same appearance as the referenced form. But all proper forms will contain the same essential information.

If No Valid Notice of Completion or Notice of Cessation Has Been Recorded:
If no valid notice of completion or notice of cessation has been recorded then contractors, subcontractors and material suppliers alike have 90 days after work on the project is completed before which they must record a mechanics lien. This 90-day period may be extended in cases where, although the project is not fully completed, the work on the project has stopped for a continuous period of 60 days and neither the owner nor his agent has accepted the project or moved onto the premises. If you have missed this 90-day deadline and there is no notice of completion or notice of cessation on file with the County Recorder in the County where the work was performed, consult with an attorney to see if any factual scenario might give more time than originally thought. (See Civil Code sections 8180, 9200, 8412, 8414, 8028, 8018, 8046.)

How to Determine the Last Date of Work or Completion

The last day of work on a project is important to determine for several reasons. If the owner records a notice of completion under Civil Code section 8182, the owner thereby triggering the quicker time frame for direct contractors (60 days) and subcontractors and suppliers (30 days) to record their mechanics liens under sections 8412 and 8414. However, it is first necessary to determine whether the notice of completion is even valid. This is because, as noted above, notices of completion must be recorded no earlier than actual completion of the work of improvement and no later than 15 days after actual completion of the work of improvement. If the notice of completion is not recorded within this 15-day window, then the notice of completion is generally not valid. (See, Civil Code sections 8182 and 9204) It is common that notices of completion are not valid because they were not recorded within this 15-day window.

Where the notice of completion is not valid or where no notice of completion has been recorded, Civil Code section 8412 and 8414 tell us that contractors, subcontractors and material suppliers alike may record their mechanics liens beginning when they have finished supplying their own work or materials to the project up until 90 days after completion of the entire work of improvement by the direct contractor and all subcontractors.

The last day of work on a project or “completion” for private works is defined under Civil Code section 8180. Section 8180 states:

8180.(a) For the purpose of this title, completion of a work of improvement occurs upon the occurrence of any of the following events:

  1. Actual completion of the work of improvement.
  2. Occupation or use by the owner accompanied by cessation of labor.
  3. Cessation of labor for a continuous period of 60 days.
  4. Recordation of a notice of cessation after cessation of labor for a continuous period of 30 days.

(b) Notwithstanding subdivision (a), if a work of improvement is subject to acceptance by a public entity, completion occurs on acceptance.

If the work of improvement is subject to acceptance by any public entity, the completion of such work of improvement shall be deemed to be the date of such acceptance; provided, however, that, except as to contracts awarded under the State Contract Act, Chapter 3 (commencing with Section 14250), Part 5, Division 3, Title 2 of the Government Code, a cessation of labor on any public work for a continuous period of 30 days shall be a completion thereof.” [emphasis added] (see Civil Code section 9200 et seq.)

Occupation or Use: Generally, the occupation or use of the work of improvement referenced above must be open and entire, and must concur with a cessation from work, but such cessation need not continue for any particular time, if it is accompanied by occupation or use of the work of improvement. See Baird v. Havas (1946) 72 Cal.App.2d 520, 164 P.2d 952 .

Where occupancy co-exists with or is consistent with further performance of the work, actual completion may not have been achieved. In such case, where no notice of completion or of cessation was filed, the claimant has 150 days (90 days under section 3115 and 3116 (now 8412 and 8416) plus 60 days under Section 3086(c) (now 8180)) from such occupancy in which to record a mechanics lien. See M. Arthur Gensler, Jr. & Associates, Inc. v. Larry Barrett Inc. (1972) 7 Cal.3d 695, 103 Cal.Rptr. 247, 499 P.2d 503.

Acceptance: It is not necessary that the acceptance (referenced above) be accompanied by cessation of labor, but it must be open and sufficient to give notice by necessary implication. See, Orlandi v. Gray(1899) 125 Cal. 372, 58 P.15; Hammond Lumber Co. v. Barth (1927) 202 Cal. 606, 262 P. 31.

Small subsequent changes to the work, including punch list items to correct defective or damaged work (as opposed to punch lists giving notice to complete uncompleted contract work) will not extend the time of actual completion or the time for filing a mechanics lien. See Hammond Lumber Co. v. Yeager (1921) 185 Cal. 355, 197 P. 111; Hunley v. Marinkovich (1942) 53 Cal.App 2d. 288, 127 P.2d 600.

Whether or not a project is ”subject to acceptance” depends on whether the improvement was required to be accepted by a public entity pursuant to a legislative act despite the fact that the contractor may have otherwise complied with all requirements necessary for approval and acceptance of the project. See, A.J. Raisch Paving Co. v. Mountain View Sav. & Loan Ass’n (1972) 28 Cal.App.3d 832, 105 Cal.Rptr. 96.

It has been held that a subcontractor working on improvements in a shopping mall could not record a valid mechanics lien based on the argument that it did so within 90 days after completion of all the work done at all the individual stores in the mall. This was because each store had a separate contract for improvement, the individual shop owners were not in contractual relationships with each other and each store was thus deemed a separate work of improvement. This is not a situation were a single lien could have been filed on the entire mall for multiple improvements made at the request of a single owner. See, Civil Code section 3130 (now 8446), Insul-Acoustics, Inc. v. Lee (1982) 136 Cal.App.3d 552, 186 Cal.Rptr. 324.

Cessation of Labor for 60 Days or 30 Days if Accompanied by a Notice of Cessation: The cessation of labor necessary to meet this standard must impart notice to a careful person. The cessation cannot be a “mere clandestine stopping of actual work.” See, Marble Lime Co. v. Lordsburg Hotel Co. (1892) 96 Cal. 332, 31 P. 164.

Note in Regard to Condominiums: Civil Code section 8448 generally provides that if a work of improvement consists in the construction of two or more separate residential units, each unit shall be considered a separate “work of improvement,” and the time for filing claims of lien against each such residential unit shall commence to run upon the completion of each residential unit. However, this has been held inapplicable to condominiums. See, E. D. McGillicuddy Constr. Co. v. Knoll Recreation Ass’n, Inc. (1973) 31 Cal.App.3d 891, 107 Cal.Rptr. 899.

Conclusion

All of the above rules help to determine whether a mechanics lien has been timely recorded or has been recorded late and is therefore unfortunately unenforceable. The best single bit of advice in recording a timely mechanics lien is to avoid delay. Once you have finished your work on a project, you have the right to record a lien on that project. Your rights won’t begin to expire until the project suspends or terminates. Once that happens, the danger of missing the mechanics lien recording deadline become greater with every day of delay.

Article by William L. Porter, Esq. in 2024. Mr. Porter is a principal in The Porter Law Group, Inc. in Sacramento, California. He can be reached by phone at (916) 381-7868.

The Porter Law Newsletter

Get highlights and insights of the most important legal information delivered right to your email inbox.
 
#printfriendly h6 { font-size: 20px !important; font-weight: bold !important; color: #d98918 !important; } #pf-body #pf-header-img { max-width: 35% !important; margin-bottom: 2rem !important; } #printfriendly #pf-title { margin-bottom: 1.5rem !important; } #pf-src { display: none; } div.print-header { text-align: center; margin: 0 0 16px 0; font-size: 1rem; display: block !important } .pf-content > ul > li { margin-bottom: 15px; }