The Importance of Preliminary Notices on Private Works Projects

Time and time again I receive calls from subcontractors and suppliers who find themselves faced with a customer who is either unwilling or unable to pay for labor or materials supplied for a private works project. As an attorney, the first question I usually ask is “did you serve a Preliminary Notice?” The second question I usually ask is “did you serve the Notice within twenty (20) days after first furnishing labor, service, equipment or materials to the job site?” The answers to these questions will often determine the ability to collect on the claim.

Read Article

Preliminary Notices: Common Avoidable But Fatal Mistakes

In the California building and construction industry, the “Preliminary Notice” is an absolute prerequisite for Subcontractors and Suppliers to protect their right to be paid for work performed and materials provided to a construction project.  Without the proper drafting and service of a Preliminary Notice, Subcontractors and Suppliers cannot protect their right to payment using such indispensable collection remedies as the Mechanics Lien, Stop Payment Notice and Payment Bond Claim.

Read Article

The Importance of a Notice of Completion to Contractors, Subcontractors and Suppliers

The recording of a valid “Notice of Completion” with the County Recorder is an event of significance to owners, contractors, subcontractors and suppliers alike. The recording of a Notice of Completion is one of several methods used to trigger the time period for the recording of mechanics liens and service of stop payment notices. Although the recording of a Notice of Completion is not absolutely required on any given project, all those working in the construction industry should understand its significance.

Read Article

Project Completion Determines Mechanics Lien Recording Deadline

The California Mechanics Lien is one of the most valuable collection devices available to contractors, subcontractors and suppliers who are unpaid for work performed and materials supplied in relation to a California Private Works project. The mechanics lien allows the claimant to sell the property where the work was performed in order to obtain payment. The process starts with the recording of a mechanics lien in the office of the County Recorder where the property in question is located. As noted below, certain deadlines must be met.

Read Article

Penalty for Failure to Release Expired Liens

I was recently contacted by a commercial building owner in the process of trying to sell the building. Two years prior to this, a subcontractor had recorded a mechanics’ lien with the local County Recorder’s office in relation to the owner’s property. The subcontractor recorded the mechanics lien after the subcontractor was not paid by a prime contractor for work the subcontractor had performed on the property. Unfortunately for the subcontractor, the subcontractor then failed to file a lawsuit to foreclose on the lien within the requisite ninety (90) day time period for filing a lawsuit to foreclose on the mechanics’ lien. Since the subcontractor missed this 90 day deadline to file the mechanics lien foreclosure lawsuit, the mechanics lien expired.

Read Article

Corporate Transparency Act Who Must File, When to File, How to File

The Corporate Transparency Act (“CTA”) came into effect on January 1, 2024, impacting numerous small businesses throughout the United States. The claimed objective of the CTA is to address the covert nature of corporate ownership, a facet exploited for various illicit activities such as money laundering, terrorism financing, and other financial wrongdoings. Under the newly enacted legislation, businesses meeting specific but common criteria are obligated to submit a Beneficial Ownership Information (“BOI”) Report to the U.S. Department of Treasury’s Financial Crimes Enforcement Network (“FinCEN”).

Read Article

The Porter Law Newsletter

Get highlights and insights of the most important legal information delivered right to your email inbox.